The information regarding projected annual revenue is based on committed contractual terms, internal estimates for capital expenditures, and assumes full capacity utilization of the 526 MW of critical IT load. Expected delivery will be completed in phases, with the full capacity for Phase I expected to be delivered by the end of the first half of 2026, Phase II throughout 2027 and Phase III starting in 2028. Actual results may differ materially due to business, economic and competitive uncertainties and contingencies, which are beyond the control of the Company and its management and subject to change. Please refer to the risks contained in filings we make with the SEC from time to time, including in our Quarterly Report on Form 10-Q for the quarter ended June 30, 2025, filed with the SEC on August 5, 2025 and available on Galaxy’s profile at www.sec.gov/edgar.